TJ O’Connor & Associates were engaged by Wexford Borough Council to act as client’s representative in connection with a project to construct a WWTP which caters for a loading of 45,000 p.e. In addition the plant incorporates a centralised sludge treatment facility capable of treating sewage sludge for a loading of 80,000 PE. A 2km long, 900mm diameter inlet sewer and a 2.5km long 1100mm diamter outfall pipeline to the harbour was constructed under the WWTW contract.

The new treatment plant provides adequate reserve capacity to effectively treat the wastewater for the future development of Wexford town and its environs. Construction of Phase 1 for 30,000pe commenced in February 2002 and was completed in June 2003 under a DBO contract. Phase 2 extended the capacity of the plant to 45,000 PE and was completed in 2009 and is now fully commissioned.

Start/End Date:

2002 – 2009

Contract Value:

€24M

Role:

Client’s Representative under the FIDIC Form of Contract with amendments.

Key Features:

Works undertaken at the new WWTP (45,000 PE) and Sludge Hub Treatment Centre (80,000) PE included: